The Chinese builder has started work, partially, on Lot 3 North of the Bucharest Motorway.
VIDEO George Tănase
Profit.ro previously announced that the authorities approved the launch of new works on the Bucharest Highway, on the section won by the Chinese company China Civil Engineering Construction Corporation.
THE DOCUMENT CAN BE VIEWED HERE
They will be arranged
a section of .6 km long
READ ALSO PHOTO ANNOUNCEMENT The works of the Turkish constructor on another lot of the Bucharest Motorway are nearing completion!
road junction at the intersection with DN2 Bucharest-Urziceni (km 40+230)
7 structures (passages, bridges)
short term parking
The route of Lot 3 North is included in the territory of Ilfov county between DN2 near the town of Afumati and DN3, in the area of the town of Cernica.
Autostrada A0 Bucharest Beltway The South Segment of the A0 highway is divided into three lots, for which the winners of the tenders were announced in April-May 2019:
Lot 1, A2 – CF902 (Jilava), 16.9km, winner Alsim Alarko Sanayi Tesisleri ve Ticaret AȘ (Turkey), price 830,679,662.15 lei without VAT. Contract signed in Aug 2019
Lot 2, CF902 (Jilava) – DN6, 16.3km, winner Alsim Alarko Sanayi Tesisleri ve Ticaret AȘ (Turkey), price 750,849,942.12 lei without VAT. Signed contract
Lot 3, DN6 – A1, 17.97km, winning association Aktor SA (Greece) – Euro Construct Trading SRL, price 853,422,022.52 lei without VAT, execution term 42 months. Signed contract. The contract was fully taken over by Aktor SA.
The North segment of the A0 highway is divided into four lots:
Lot 1, DJ601 – DN1 (Corbeanca), 17.5km, under construction, winner: Impresa – Pizzarotti (Italy) – Retter Project Management, price: 815.08 million lei without VAT. Duration: 12 months for design, 22 months for construction. Contract signed in September 2023
Lot 2, DN1 (Corbeanca) – DN2 (Afumati), 19.0km, under construction, winner: the association SA&PE Construct SRL – Spedition UMB SRL – Tehnostrade SRL, price: 831,920,653.34 without VAT, design duration: 12 months , construction duration: 22 months. Contract signed in May 2021. 9.5km between DN1 and A3 opened in November 2023
Lot 3, DN2 (Afumati) – DN3 (Cernica), 8.6km, under construction. Builder selected in November 2022: China Civil Engineering Construction Corporation (China), price 397,996,117.63 lei without VAT, design duration: 12 months, execution duration: 18 months. Contract signed in March 2023
Lot 4, DN3 (Cernica) – A2, 4.47km, winner Asociea SA&PE Construct SRL – Spedition UMB SRL – Tehnostrade SRL, price 312.6 million lei without VAT, design duration: 12 months, execution duration: 18 months. Contract signed in August 2020.