The largest parking lot under construction in Cluj is at 50%

--

The construction site of the parking lot with 863 parking spaces under construction at the airport has reached 50%, the City Hall announces. The builder is TCI General Contractor and the value of the investment is over 14.5 million euros.

The investment is carried out by Cluj-Napoca City Hall in the Traian Vuia area (no. 149-151), the project being taken over by the County Council after the institution could not secure the necessary budget. Already the mayor has presented several images from the site, including a clump of large bale trees that were being planted on the site. The town hall informed that the construction site has reached 50%, works executed from the total investment, without specifying exactly what remains to be built.




The project includes:
– setting up a parking platform and access from the national road;
– arrangement of public transport stations
– the construction of a bus station type terminal, including a building for the transport terminal, with a canopy for passengers and coaches
– setting up a public square
– 300 new trees planted.

In total, 863 parking spaces are provided:
– 788 parking spaces for vehicles;
– 37 parking spaces for people with disabilities;
– 30 parking spaces for electric and hybrid vehicles;
– 8 platforms for buses.

Traian Vuia Street will be systematized as follows: Park&Ride access area, new roundabout, sidewalks, relocation of the public transport station.

see also:

No comments

author photo two


The article is in Romanian

Romania

Tags: largest parking lot construction Cluj

-

PREV The daughter-in-law of the Romanian millionaire who cheated on his wife for 16 years with the most famous mistress in Romania appeared with her breasts exposed!
NEXT Woman from Olt raped and robbed in her own home. The aggressor was detained (VIDEO)