The most awaited highway in Romania. The good news has come

--

A new highway appears in Romania. Sorin Grindeanu, Minister of Transport, provided more information after the working visit to the construction site of the Moldova highway (A7), Lot 1 of the Ploiesti-Buzau section.

Sorin Grindeanu provided more information about a new highway that is to appear in Romania. The statement came after a working visit to the construction site of the Moldova highway (A7), Lot 1 of the Ploiesti-Buzau section.

A new highway appears in Romania

The first vice-president of the PSD says that he has noticed a “good evolution” on approximately 50 kilometers of the Ploiesti-Buzau Highway sector (63.25 km).

On Lot 1 Dumbrava – Mizil (21 km) the physical stage of works is approaching 60% and on Lot 2 Mizil- Pietroasele (28.35 km) the physical stage has exceeded 61%.

The minister emphasizes that those working on the two lots are “very well mobilized”. This shows they are serious about this build, he says.

For Lot 3 Pietroasele – Buzău Municipality, the Turkish builder has already started the preliminary works for the construction of the 13.9 km.

PHOTO SOURCE: Inquam Photos / George Călin

The first 2 lots from Ploiești-Buzău will be put into circulation

At the moment, all 13 lots/sections of the A7, Ploiesti – Pașcani, are in various stages of construction.

Also, the first 2 Lots from Ploiești-Buzău will be put into circulation by the end of this year, according to the contractual terms.

“Good evolution on approximately 50 kilometers of the Ploiești-Buzău Motorway sector (63.25 km). On Lot 1 Dumbrava – Mizil (21 km) the physical stage of works is approaching 60% and on Lot 2 Mizil- Pietroasele (28.35 km) the physical stage has exceeded 61%.

In particular, the Romanian builders working on the two lots are very well mobilized, which proves that they approach this construction seriously. For Lot 3 Pietroasele – Buzău Municipality, the Turkish builder has already started the preliminary works for the construction of the 13.9 km.

At the moment, all 13 lots/sections of the A7, Ploiesti – Pașcani are in various stages of construction. By the end of this year, according to the contractual terms, the first 2 Lots from Ploiești-Buzău will be put into circulation”, wrote Sorin Grindeanu on Facebook.

The first section of the Moldovei Highway will be open to traffic

We remind you that the first section of the Moldova Highway will be open to traffic. It is about the section Buzău – Focşani. Marcel Ciolacu offered several explanations and emphasized that this year 147 kilometers of the Moldavian Highway will be put into use.

The head of the PSD also spoke about the importance of the express road in the Oltenia area and the A0 highway. According to the prime minister, it is very important that the prices are as low as possible, and that those involved are as competitive as possible.

Regarding the Comarnic – Braşov highway, the prime minister said that the authorities are still looking for a public-private partnership.